N2 - Rehabilitation of parking garages – when and why?. Existing models for the evaluation of the durability of reinforced concrete structures allow to prognose the limit state condition of the structure during its service life by means of the reliability index. Furthermore, in the decision-making process, a fixed (limit) value for the reliability can be defined, which refers to a maximum acceptable probability of occurrence of a selected (undesirable) event (limit state). The worse the condition, the higher the expected rehabilitation costs. If it is possible to describe the expected rehabilitation costs as a function of the reliability index, the repair times can be determined in a cost-optimal way. Therefore, expert reports with extensively documented inspection results and associated costs of underground parking garage repairs were analyzed. The main cause of the repairs was in all cases chloride-induced reinforcement corrosion. Three approximation methods were used to estimate the reliability of column and wall bases and compared with each other. At the structure, i.e. object level, it was not possible to establish a clear relationship between reliability and repair costs. However, at the structural component level, this was achieved for a single project. This provides a starting point for cost-optimized determination of repair times.
AB - Rehabilitation of parking garages – when and why?. Existing models for the evaluation of the durability of reinforced concrete structures allow to prognose the limit state condition of the structure during its service life by means of the reliability index. Furthermore, in the decision-making process, a fixed (limit) value for the reliability can be defined, which refers to a maximum acceptable probability of occurrence of a selected (undesirable) event (limit state). The worse the condition, the higher the expected rehabilitation costs. If it is possible to describe the expected rehabilitation costs as a function of the reliability index, the repair times can be determined in a cost-optimal way. Therefore, expert reports with extensively documented inspection results and associated costs of underground parking garage repairs were analyzed. The main cause of the repairs was in all cases chloride-induced reinforcement corrosion. Three approximation methods were used to estimate the reliability of column and wall bases and compared with each other. At the structure, i.e. object level, it was not possible to establish a clear relationship between reliability and repair costs. However, at the structural component level, this was achieved for a single project. This provides a starting point for cost-optimized determination of repair times.
KW - chloride-induced corrosion
KW - parking garages, structural rehabilitation
KW - rehabilitation costs
KW - reliability index
UR - http://www.scopus.com/inward/record.url?scp=85137104711&partnerID=8YFLogxK
U2 - 10.1002/best.202200074
DO - 10.1002/best.202200074
M3 - Artikel
AN - SCOPUS:85137104711
SN - 0005-9900
VL - 117
SP - 946
EP - 955
JO - Beton- und Stahlbetonbau
JF - Beton- und Stahlbetonbau
IS - 12
ER -