Importance of secondary processes in heavy equipment resource scheduling using hybrid simulation

Anne Fischer, Zhuoran Li, Stephan Kessler, Johannes Fottner

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

4 Scopus citations

Abstract

As part of the Architecture, Engineering, and Construction (AEC) industry, heavy civil engineering with its equipment-intensive processes is a current focus of discussion concerning emission reduction. Adopting Industry 4.0 technologies for resource scheduling can significantly increase the savings potential significantly. One of these digital technologies is the Discrete Event Simulation (DES). DES is a proven tool to analyze complex systems in advance but is not widely used in practice. Therefore, the presented work aims at presenting a three-part hybrid simulation framework. One part of the framework, the meso-simulation, has been evaluated using a case study in the field of pile drilling production. The work not only captures the drilling process, and therefore shows the importance of planning the secondary processes in AEC.

Original languageEnglish
Title of host publicationProceedings of the 38th International Symposium on Automation and Robotics in Construction, ISARC 2021
EditorsChen Feng, Thomas Linner, Ioannis Brilakis
PublisherInternational Association for Automation and Robotics in Construction (IAARC)
Pages311-318
Number of pages8
ISBN (Electronic)9789526952413
StatePublished - 2021
Event38th International Symposium on Automation and Robotics in Construction, ISARC 2021 - Dubai, United Arab Emirates
Duration: 2 Nov 20214 Nov 2021

Publication series

NameProceedings of the International Symposium on Automation and Robotics in Construction
Volume2021-November
ISSN (Electronic)2413-5844

Conference

Conference38th International Symposium on Automation and Robotics in Construction, ISARC 2021
Country/TerritoryUnited Arab Emirates
CityDubai
Period2/11/214/11/21

Keywords

  • Agent Based Modelling (ABM)
  • Discrete Event Simulation (DES)
  • Hybrid simulation
  • Job and activity scheduling
  • Modeling of manufacturing operations
  • Production planning and control
  • Project schedule optimization